Tunnel Construction

Tunnel Construction
Tunnel construction works are being carried out. About 70% of total excavation (including all Inlet, Adit and Outlet) is completed. From Inlet Tunnel Site : 1+420.53 m From Up Stream Tunnel Site : 0+975.017 m From Down Stream Tunnel Site : 0+935.303 m From Outlet Tunnel Site : 0+575.25 m . We are planning to do breakthrough of Inlet and Upstream tunnel before  Kartik.
More

Excavation Of Adit-1 Tunnel

Excavation Of Adit-1 Tunnel
    The excavation is being carried out. The Adit-1 tunnel has reached upto HRT junction. As of progress upto chaitra 2073, total excavation of 363m including 15m of HRT upstream & downstream from adit with rock bolt, support & shotcreting is completed.
More

सिङगटी जलविद्युत् आयोजनाको वितीय व्यवस्थापन पूरा

सिङगटी जलविद्युत् आयोजनाको वितीय व्यवस्थापन पूरा
Posted on
काठमाडौ, साउन २४ ।  दोलखा जिल्लाको सिङ्गटी खोलामा निर्माण हुने  सिङ्गटी जलविद्युत् आयोजनाको निर्माण कार्य असोजदेखि शुरु हुने भएको छ । ‘आयोजना निर्माणको पुर्वतयारीको काम ९८ प्रतिशत पूरा भइसकेकाले  असोजदेखि निर्माण शुरु गर्न लागिएको हो,’ आयोजना प्रबद्र्धक कम्पनी, सिङ्गटी हाइड्रो इनर्जी कम्पनीका महाप्रबन्धक रमेश अधिकारीले भने । १६ मेगावट क्षमताको उक्त आयोजनामा नौ ओटा बैंकले सहवित्तीयकरण कर्जा लगानीक...
More