The design discharge of the Singati Khola Hydropower Project is 11.3 m3/sec .The total headrace tunnel length of the project is 5824m & 719 m of penstock pipe. The headworks & about 4.8 km length of tunnel of the project is located on the Babare VDC of Dolakha district, whereas all other project components including about 1 km tunnel lies in Lamidanda VDC. Access road to headworks passes through Laduk & Chilankha VDC. The project is a run-of-river type having the capacity of 25 MW.
Salient Features of the Project
Location of the Project |
27 0 44′ 00″ to 27 0 47′ 17″ N
86 0 07′ 05″ to 86 0 09′ 55″ E |
Installed Capacity |
25.0 MW |
Hydrology
Catchment Area at Intake |
189.5 km2 |
Catchment Area at Powerhouse |
231.9 km2 |
Design 100 yrs. Flood at Intake |
455 m3/sec |
Design 100 yrs. Flood at PH |
574 m3/sec |
Downstream Release |
308 lps |
40% Dependable Flow (Q40%) |
11.30 m 3 /sec |
Design Discharge |
11.3 m3/sec for From Intake to Tunnel Inlet
7.3 m3/sec for HRT, Penstock Pipe and PH Units |
Power Development
Type of Power Generation |
Run-of-river |
Turbine Discharge |
7.30 m³/s |
Total Gross Head |
268.05 m |
Net Head at Design Discharge |
257.66 m |
Average Annual Energy |
101.868 GWh |
Dry Energy |
19.897 GWh |
Wet Energy |
81.971 GWh |
Weir
Type of Weir |
Overflow Ogee |
Length of Weir |
38.0 m |
Weir Crest Level |
EL. 1246.05 |
Weir Foundation Level |
EL. 1235.80 m |
Undersluice Structure
Nos. of gates |
1 no. |
Size of gate opening (NoxWxH) |
1 x 4.0 m x 4 m |
Undersluice Crest level |
EL. 1242.85 m |
Power Intake
Intake Type |
Side Intake (Orifice Type) |
Intake Gates or Openings |
3 nos. |
Gates opening size (W x H) |
4.0 m x 1.1 m |
Intake Invert Level |
EL. 1244.75 m |
Total Intake Width |
14.0 m |
Approach Canal
Number |
single |
Section Type |
Rectangular |
Size (W x H) |
13.0 m x (6.1 to 2.3) m |
Length |
47 m |
Hydraulic Slope |
1:1000 |
Gravel Trap (GT) |
Inbuilt Provision of GT |
Desanding Basin
Type |
Dufour, Continuous flushing |
Desanding Chambers |
2 nos |
Size (L x B x H)- Each |
96 m x 9.7 m x 6.7 m |
No. of Flushing Channel |
2 nos |
Size (B xD) |
0.48 x 0.48 (Slope 1 in 50) |
U/S transition |
10.0 m |
D/S transition |
7.5 m |
Head Pond
Section |
Rectangular |
Size (W x H) |
13.1 m x 9 m |
Length |
32 m |
Box Conduit Invert Level |
EL.1237.725 m |
Operating Water Level |
EL.1245.525 m |
Pressure Box Conduit
Type |
RCC |
Size (BxH) |
3m x 3.2m |
Length |
65m |
Tunnel Invert Level |
EL 1237.660 |
Headrace Tunnel
Type |
Invert ‘D’ Shape (Pressure Flow) |
Size (BxH) |
2.6 x 2.9 m |
Lining |
Fiber Shortcrete |
Length |
5824 m |
Slope of Tunnel |
1 in 600 |
Number of Adits |
2 |
Adit -1 Length |
295 m |
Adit -2 Length |
65 m |
Penstock Pipe
Before Double Bifurcation |
Type |
Steel Circular |
Number |
1 nos. |
Diameter |
1.85 m |
Length |
657.0m |
Thickness |
12 mm to 26mm |
After Double Bifurcation |
Type |
Steel Circular |
Number |
2 nos. |
Diameter |
1.3 m |
Length |
42.0m |
Thickness |
26mm |
Surge Shaft
Section Type |
Circular |
Diameter |
6.0 m |
Height from Base |
31.6 m |
Max. Upsurge Level |
EL. 1257.525 |
Min. Downsurge Level |
EL. 1232.525 |
Powerhouse
Type |
Surface |
No. of Units |
2 |
Type of Turbine |
Pelton |
Size (LxBxH) |
40.0 x 20.0 x 11 m |
Tail Water Level (Turbine CL) |
EL.978.0 m |
Tailrace
Type |
RCC Box/Rectangular |
Length |
15.0 m |
Size (BxH) |
4.0 m x 2.60 m |
Discharging River |
Singati |
Transmission Line
132 kV |
0.2 Km long 132 kV single circuit connected to Singati sub-station |
Generator |
Brushless synchronous, 3 phase 2×9,400 KVA 11 KV |
Transformer
Power Rating |
1 x 18,800 KVA, 132/11 KV, 50 Hz |
Specification |
3 phase, ONAN/ ONAF Cooled |
Project Cost in Mil. NPR (Excluding IDC) |
2,633.173 |
Financial Indicators
Project Cost MNPR/MW |
164.573 |
Construction Period |
3 Years |
IDC (MNPR) |
260.266 |
Financial Cost (MNPR) |
2,893.438 |
Financial Cost (MNPR)/MW |
180.840 |
Interest Rate |
10% |
IRR |
17.34% |
BC Ratio |
1.75 |
NPV (MNPR) |
1,586.236 |
Pay Back Period (years) |
5.61 |
About Us
Singati Hydro Energy Pvt. Ltd was established under the company Act 2063, in 2067 to develop the Singati Khola Hydropower Project, Dolakha.
The company was previously managed another management team. New management team is managing the company since 2069. Right now there are six members in the board of directors under the chairmanship of Mr. Sudip Raj Gautam.
As the company is currently developing the Singati Khola Hydropower Project (25 MW) capacity, widely known as super six project the Company using the service of other individuals, consultants, which are specialist in their field. They are available to the company as and when required for consultation, in order to ensure that the company’s progress. WELINK Associates Pvt. Ltd is our design consultant for this specific project.
Company Biography:
Name of the Company |
Singati Hydro Energy Ltd. |
Type of Organization |
Public Limited |
Registered Address |
Gahanapokhari, 05-Kathmandu. |
Office Address |
Gahanapokhari, Kathmandu, Nepal.
Tel : 01-4543203
email :shehydro@gmail.com |
Date of Registration |
Jestha-05, 2067 |
Company Registration No |
72937/066-067 |
PAN Number |
304300875 |
Industry Reg. Certificate |
1908/327/069-070 |