Excavation Of Adit-1 Tunnel

   

Excavation of Adit-1 tunnel is being carried out.

Muck disposal tipper

The excavation is being carried out. The Adit-1 tunnel has reached upto HRT junction. As of progress upto chaitra 2073, total excavation of 363m including 15m of HRT upstream & downstream from adit with rock bolt, support & shotcreting is completed.