Tunnel construction works are being carried out. About 70% of total excavation (including all Inlet, Adit and Outlet) is completed.
From Inlet Tunnel Site : 1+420.53 m
From Up Stream Tunnel Site : 0+975.017 m
From Down Stream Tunnel Site : 0+935.303 m
From Outlet Tunnel Site : 0+575.25 m .
We are planning to do breakthrough of Inlet and Upstream tunnel before Kartik.