Tunnel Construction

Tunnel construction works are being carried out. About 70% of total excavation (including all Inlet, Adit and Outlet) is completed.

From Inlet Tunnel Site : 1+420.53 m

From Up Stream Tunnel Site : 0+975.017 m

From Down Stream Tunnel Site : 0+935.303 m

From Outlet Tunnel Site : 0+575.25 m .

We are planning to do breakthrough of Inlet and Upstream tunnel before  Kartik.

Outlet Tunnel Portal

Tunnel