Singati Hydro Energy Limited 25 MW
Powerhouse Construction

The construction of the Powerhouse is started and is going in full speed.
Construction up to 1st tie beam has been completed.
Appointment of an Issue Manager

Issue Manager is appointed to "Civil Capital Market Ltd." for the issue of shares for local and general public on July 13 , 2018.
Tunnel Construction

Tunnel construction works are being carried out. About 70% of total excavation (including all Inlet, Adit and Outlet) is completed.
From Inlet Tunnel Site : 1+420.53 m
From Up Stream Tunnel Site : 0+975.017 m
From Down Stream Tunnel Site : 0+935.303 m
From Outlet Tunnel Site : 0+575.25 m .
We are planning to do breakthrough of Inlet and Upstream tunnel before Kartik.
Penstock Alignment
Main office Camp

Main campsite is located at Katike. There are seven buildings in total & some other buildings
for stores & laboratory.
Excavation Of Adit-1 Tunnel

The excavation is being carried out. The Adit-1 tunnel has reached upto HRT junction. As of progress upto chaitra 2073, total excavation of 363m including 15m of HRT upstream & downstream from adit with rock bolt, support & shotcreting is completed.